Fast-track Approvals Act
The Fast-track Approvals Act 2024 (FTAA) enacted on 23 December 2024 is an approval process for a range of infrastructure, housing, and development projects with significant regional or national benefits. It is an alternative process to consenting instead of the Resource Management Act 1991 (RMA).
The Environmental Protection Authority (EPA) and the Ministry for the Environment administer the applications under the FTAA. Other agencies such as the Department of Conservation are also given the opportunity to input into the process, including regional councils like ours.
There are two application processes that are administered by central government:
- Referral application: an application to the Minister of Infrastructure that if approved, enables projects of regional or national significance the ability to use the FTAA process. Projects that are successful referred may then seek consent through a substantive application.
- Substantive application: referred projects can lodge a substantive application with the Environmental Protection Authority (EPA) for an expert panel to consider and decide on final approvals.
An overview of the Fast-track process is available here.
Environment Southland’s role in the process
We do not make any decisions on a Fast-track application but respond to requests from the Environmental Protection Authority to comment.
In the referral process, the Minister for Infrastructure considers and makes decisions. In the substantive process, an expert panel is appointed to consider and make decisions.
We:
- Provide pre-application advice to an applicant who must notify us before they lodge their application (referral or listed).
- Provide advice on applications from the Minister for Infrastructure (referral applications) and the Environmental Protection Authority and expert panels (substantive applications) as required under the FTAA throughout the application process.
- When granted, we administer and monitor the various approvals decided by the expert panels, along with other relevant agencies and parties.
Fast-track application requirements
Before lodging your application
Before lodging a referral or listed application, applicants must meet pre-lodgement requirements set out in Section 11 of the FTAA.
While the FTAA states that 20 working days’ notice is required, we recommend that you engage with us sooner, so that we can provide meaningful input into your application.
Submitting quality Fast-track applications
The information provided in an application can significantly shape our ability to make recommendations to the EPA and expert panels at key steps in the fast-track process.
Notification requirements under Section 30 of the FTAA
Section 30 of the FTAA requires an applicant to notify each regional council that is a consent authority in writing in order to check that there are not existing resource consents for the same activity using some or all of the same natural resource.
Once the regional council has received notification, it is then required to notify the applicant in writing of any existing resource consents to which section 124C(1)(c) or 165ZI of the RMA applies within 10 working days of receiving the notification. This step must be completed before the substantive application can be lodged.
Costs for fast-track processing
Costs prior to lodging with the EPA: We can recover all fair and reasonable costs for the work we do with applicants (including that of any consultants used to assist) prior to the application being lodged. Please see our Fees and Charges Schedule for further details relating to costs and charging.
Costs after application is lodged: Once an application is lodged (either referral or substantive), councils can recover their costs of inputs into the EPA process, using the cost recovery process administered by the EPA.
For full details, refer to the EPA's fees, charges and cost recovery information.
Contact us: If your proposal is in Southland and you plan to use the Fast-track process, contact our Consents Team. 03 211 5115 or 0800 76 8845. You can also email: service@es.govt.nz
Useful links
For more information about the fast-track approvals process under the Fast-track Approvals Act 2024 (FTAA), see the following links:
- Fast-track website – A dedicated site maintained by the Ministry for the Environment and the EPA
- Fast-track approvals process – Ministry for the Environment's overview
- Fast-track Approvals Act 2024 – Full legislation on the New Zealand Legislation website
For questions about the fast-track referral or substantive processes, contact, 0800 327875 or email contact@fasttrack.govt.nz
Current Southland Fast-track applications
You can view the list of projects already listed in Schedule 2 of the FTAA, or you can search by region.