Mataura River flood resilience project
Detailed design and modelling report
The Gore bridges channel improvements were developed using detailed hydraulic modelling undertaken by Land River Sea Consulting.
Download the Gore – Mataura River Widening Final Design Report 2025 (PDF)
The report sets out the design for widening the Mataura River channel at and downstream of the Gore railway and State Highway bridges. It assesses hydraulic performance across a range of flood events and maintains the existing low-flow channel while reshaping selected parts of the wider channel to improve performance during high flows.
During construction, the proposed work in Area 1 was reviewed further because of its proximity to the Gore District Council stormwater outfall and the State Highway bridge pier. That review resulted in a reduced scope for Area 1 while retaining the majority of the hydraulic benefit from the wider channel improvement works.
The detailed design report follows an initial 2024 investigation into the Gore rail bridge capacity. Download this report here.
That work identified limited capacity through the bridge reach as an important contributor to flood risk in Gore during large events and assessed options for improving channel capacity around and downstream of the bridges.